Project Update – April 16, 2019

Construction activity begins, weather permitting. Work includes:

  • Setting up traffic control with likely lane closures for the duration of the project
  • Setting up erosion control around the perimeter of the project
  • Tree removal identification, walk-through and clearing (77 trees to be removed, replaced by 106 new trees and more than 1,100 new shrubs, plants and grasses)
  • Lighting removal (installing new lighting to match the easterly Singletree Lane lights)
  • Sidewalk removal


Project Summary

Singletree Lane Concept Design [PDF]
Singletree Lane Streetscape

The first phase of the Singletree Lane streetscape improvements was constructed in 2010 from Eden Road to Flying Cloud Drive. Design of the improvements on Singletree Lane between Prairie Center Drive and Eden Road will work within the context of the current Singletree Lane conditions, the previous streetscape improvements and design framework, and lessons learned from previous projects. With this streetscape project, no roadway modifications to Singletree Lane are currently proposed. Construction is scheduled to be completed in summer 2019.

Project Contact
Carter Schulze, PE
Assistant City Engineer 
952-949-8339

Related Information
Concept Design Plan [PDF]

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer